Transparency at every milestone. Follow the evolution of each Norus residence from foundation to completion, with monthly site updates and progress documentation.

 
Scroll
2

UNDER CONSTRUCTION

 
2

Construction Complete

 
2

Residences Remaining at Beach Point

 
98%

Sold at Sanctuary

Under Construction

Riverbend
Ivanhoe
September Update

Riverbend Ivanhoe continued to make strong progress throughout September,  with works advancing across both the exterior and apartment interiors. External wall framing, window installation and roofing are moving towards completion while internal works are now becoming more visible across the ground-floor residences.

This progress is being matched by strong buyer momentum, with Riverbend Ivanhoe now 90% sold. As construction moves into more detailed stages, the building is becoming increasingly recognisable as the future residential address taking shape in Ivanhoe.

Highlights

External wall framing progressing across all levels

Window installation advancing towards completion 

Metal roofing works progressing across the development

Sanding and painting commencing within ground-floor residences

Ground-floor joinery installation commencing during September

Sold 90%
 

Next Stage

Complete remaining external wall framing and window installation

Continue internal finishes and ground-floor joinery works

Prepare for tower crane dismantling around late September or early October

Construction continues to progress steadily across multiple areas of the building, with exterior works and internal finishes now moving forward together. Each milestone brings Riverbend Ivanhoe closer to its completed form while maintaining strong momentum on site.

Under Construction

Parkview
Burwood
September Update

Construction continues to progress steadily at Parkview Burwood, with structural works advancing through the level 3 slab while basement services rough-ins are now underway. As the structure continues to rise, activity is also beginning to expand into services and internal works across the building.

With Parkview Burwood now 80% sold, September marks another important step forward as different stages of construction begin progressing alongside one another and the building becomes increasingly defined.

HIGHLIGHTS 

Level 3 slab works continuing as the structure advances

Basement services rough-ins now underway

Structural works progressing alongside early building services

 

—    Construction moving gradually towards internal works
Sold 80%
 

Next Stage

Progress formwork stripping up to the ground floor

Commence services rough-ins and internal wall framing on the ground floor

Begin window installation as the building moves towards a more enclosed form

Construction remains well coordinated as structural works continue and further trades move through completed areas. We will continue to share progress as Parkview Burwood advances through these increasingly visible stages.

Register Interest
Construction Complete

Sanctuary
Sandringham
Final Release

Sanctuary Sandringham is now construction complete, marking an exciting milestone for this boutique bayside address. With settlements and move-ins now underway, purchasers can experience the completed homes in person and appreciate the refined finishes, thoughtful layouts and calm coastal setting with confidence.

Highlights

Construction complete settlements and move-ins now underway

Move-in ready apartments and townhouses available in the final release

European marble benchtops, Bosch appliances and European oak engineered floorboards

Double-glazed windows and double insulation for year-round comfort

Close to Bay Road Heathland Sanctuary, Sandringham Village, local cafés, beaches and transport

Sold 98%
 
Enquire Now
Construction Complete

Beach Point
Sandringham
Reaches Completion

Beach Point Sandringham has reached construction completion a defining milestone for this boutique collection of bayside residences on Beach Road. Settlements are now underway and move-ins have commenced. Remaining opportunities to secure a home are limited.

Highlights

Construction complete with settlements underway and move-ins commencing

Only 2 penthouses remain in the final stage of availability

Generous kitchens with marble finishes, encased island benches and 900mm Bosch appliances

Walk-in pantries and practical storage designed for everyday living and entertaining

Moments from Sandringham Beach, Sandringham Village, Hampton Street dining and both Sandringham and Hampton stations

Sold 90%
 
Enquire Now

Stay Informed
at Every Milestone

Receive monthly construction updates, exclusive previews and first access to new releases across all Norus projects. We keep you close to the progress.

Facebook Follow Us
Instagram @norus.projects