Beach Point Sandringham: October Construction Update
Interiors taking shape as Beach Point moves closer to completion
October has seen strong progress on site at Beach Point Sandringham, with internal works advancing across all levels and apartments now starting to feel like finished homes. With key structural stages nearing completion, the focus has shifted firmly to finishes, joinery and fit-off are all essential steps toward welcoming residents in early 2026.
Highlights
-
All apartment walls and ceilings are now complete throughout the building.
-
Internal waterproofing is finished up to level 2, supporting upcoming tiling and fit-off
-
Tiling is complete on level 1 and progressing through level 2
-
The joinery installation has commenced on the ground floor and will continue through levels 1, 2 and 3
-
Painting is advancing progressively as each plastered stage is finalised
Next Stage
-
Balustrade installation
-
Timber flooring installations
-
Lift completion
-
Fixture/appliance fit-off
Construction remains firmly on track for early 2026 completion. Limited apartments remain, with incentives still available – now is the ideal time to book a private appointment and secure your home.